Installed cost
$5,820 – $10,380
$7.00 – $13.00 / sq ft
Concrete (+10%)
13.58 yd³
Net 12.35 yd³ at 5 in
80-lb bags
612
815 × 60-lb
Best way to buy
Ready-mix
2 trucks, $2,183

A 20 × 40 ft slab (800 sq ft) is a two-car-wide driveway: two cars side by side, two deep. At 5 in it is 13.58 yd³ with waste in 2 trucks, and the joint grid splits it into 8 panels.

Concrete for a 20x40 Slab at 4, 5 and 6 Inches

ThicknessNet volumeWith 10% wasteReady-mix order80-lb bags60-lb bags40-lb bagsInstalled
4 in 9.88 yd³ 10.86 yd³ 11 yd³ 489 652 978 $5,410–$9,870
5 in (typical) 12.35 yd³ 13.58 yd³ 13.75 yd³ 612 815 1,223 $5,820–$10,380
6 in 14.81 yd³ 16.30 yd³ 16.5 yd³ 734 978 1,467 $6,230–$10,890
Bag yields: 80 lb = 0.60 ft³, 60 lb = 0.45 ft³, 40 lb = 0.30 ft³, rounded up to whole bags. Ready-mix rounded up to the next quarter yard. Installed low end: plain broom-finish slab with ready-mix at $150/yd³ plus a $120 delivery fee, forms and labor at $3.50/sq ft. High end: the calculator's default scope (adds a vapor barrier and #4 rebar at 18 in, labor at $5.00/sq ft) plus 25% contractor overhead and profit. DIY materials: the cheaper of ready-mix or $6.50 80-lb bags, plus forms, up to vapor barrier and rebar. Site excavation and a gravel base are extra (about $1.40 to $3.30 per sq ft).

How Much Extra to Order

The table above adds 10%, the usual allowance for a formed slab on a graded base. Pick less only for rigid forms on a laser-flat base, more for soft or uneven ground:

Waste allowance (5 in slab)Concrete80-lb bags
0% (exact volume)12.35 yd³556
5%12.96 yd³584
10%13.58 yd³612
15%14.20 yd³639

Bags or a Ready-Mix Truck?

OptionWhat you buyConcrete bill
80-lb bags 612 bags at $6.50 + mixer rental $75 $4,053
Ready-mix 13.75 yd³ at $150 + $120 delivery $2,183

Ready-mix, without question. 612 bags would cost $4,053 and take about 24 hours of mixing, far longer than concrete stays workable, so the slab would end up with cold joints. Ready-mix trucks bring it as fast as the crew can place it (2 trucks of about 8–10 yd³ each). Try your own prices in the bags vs. ready-mix calculator.

What a 20x40 Slab Costs

Line item (5 in slab)BasisCost
Ready-mix concrete + delivery13.58 yd³ at $150 + $120$2,157
Forms120 lin ft at $2.20$264
Vapor barrier800 sq ft at $0.35$280
#4 rebar at 18 in800 sq ft at $1.25$1,000
Broom finish800 sq ft at $0.75$600
Labor (place & finish)800 sq ft at $5.00$4,000
Direct costBefore overhead and profit$8,301
  • Installed price: $5,820 – $10,380. The low end is a plain slab with lower-cost labor; the high end is the full scope above plus 25% contractor overhead and profit.
  • Site prep and gravel base (excavation and 4 in of compacted stone): about $1,120 – $2,640 more.
  • Permit, where one is needed: about $50 – $350.

Have a contractor's price? Put it into the concrete quote checker, or compare two or three bids side by side there.

Materials List for a 20 × 40 ft Slab

Concrete13.75 yd³ ready-mix, or 612 × 80-lb / 1,223 × 40-lb bags
Gravel base (4 in compacted)11.36 yd³, about 15.9 tons
Forms12 × 2x6 boards 12 ft long, 50 stakes, 100 screws (120 lin ft)
Rebar (#4 at 18 in)1,187 lin ft = 60 × 20-ft sticks, 98 chairs
Rebar (#4 at 12 in, heavy loads)1,727 lin ft = 87 × 20-ft sticks, 66 chairs
Or wire mesh (6x6)25 sheets of 5 × 10 ft, about $300 – $500
Vapor barrier800 sq ft plus 6 in laps
Control joints 8 panels of about 10 × 10 ft: 100 lin ft of saw cut, 1.25 in deep

Recommended Specs for a Driveway

Thickness4 in for cars; 5 in standard; 6 in for RVs and delivery trucks
Strength4,000 PSI air-entrained where de-icing salt is used, otherwise 3,500 PSI
Base4 to 6 in of compacted crushed stone
Reinforcement#4 rebar at 18 in (12 in for heavy loads or cold climates) on chairs
DrainageAt least 1/8 in per foot, away from the garage door
  • Run a center joint down the length so each lane is its own row of panels.
  • A driveway this size usually needs a permit and an approved street apron (curb cut); check before you form.
  • Wait 7 days before parking on it, longer for trucks.

Pour Day for a 20x40 Slab

  • Crew time: about 28 crew-hours to set forms, place, finish and cut joints (0.035 h per sq ft for a broom finish).
  • Trucks: 13.75 yd³ is 2 trucks, about 69–110 minutes of unloading in total. Concrete must be placed within 90 minutes of batching.
  • Reach: a truck chute reaches about 15–20 ft, enough for this slab if the truck can park beside it. If it can't, budget wheelbarrows or a line pump.
  • Joints: saw-cut 4–12 hours after finishing with a wet saw, or 1–4 hours with an early-entry saw.
  • Curing: foot traffic after 24–48 hours, cars after 7 days, full strength at 28 days.

Price Your Own 20x40 Slab

The calculator below starts at 20 × 40 ft, 5 inches. Change the thickness, finish or reinforcement, pick your state for local prices, and the Live Estimate updates with a blueprint of the joint and rebar layout.

Concrete Slab Cost & Volume Estimator

Precision multi-layer project budgeting: Materials, Sub-Base, Reinforcement, Labor & Equipment

Picking a location sets the ready-mix, excavation and labor rates below to that area's typical level. You can still type your own local prices afterwards. Slab prices by state.

ft
ft
in
$
$ /sq ft
inches
$ /yd³
$ /lin ft
$ /sq ft

Closer spacing uses more steel and raises the rebar cost.

$
$ /sq ft
$

Not charged when bagged concrete is selected.

$
$
$
$ /sq ft
%
%
Live Estimate
Estimated Total Project Budget
$8,716.09
$10.90 / sq. ft.
$117.27 / m²
Based on U.S. national average rates
Order Volume (w/ Waste)
13.58 yd³
Net: 12.35 yd³
Or Bagged Equivalent
612 bags
80-lb pre-mix bags
Total Surface Area
800 sq ft (74.3 m²)
Order volume: 10.38 m³
Estimated Wet Weight
53,167 lbs
Perimeter: 120 ft
Concrete
Labor
Prep/Base
Rebar
Forms

A scaled plan of your slab: rebar grid at the spacing you chose, support chairs about every 3 to 4 ft, and the recommended control-joint saw cuts (2.5 times the thickness in inches, in feet, capped at 15 ft). It redraws as you change the inputs.

20x40 Slab Questions

About $5,820 to $10,380 installed for a 5-inch slab with forms, a broom finish and labor ($7.00 to $13.00 per sq ft), at U.S. average prices. DIY materials run about $2,420 to $3,700. Site prep and a gravel base add about $1,120 to $2,640.

At 4 inches thick with 10% waste: 489 bags of 80-lb mix, 652 bags of 60-lb mix or 978 bags of 40-lb mix. At 5 inches: 612 bags of 80-lb mix.

At 4 inches, 9.88 cubic yards (order 11.00 with waste); at 5 inches, 12.35 (order 13.75); at 6 inches, 14.81 (order 16.50). Ready-mix is sold in quarter yards, so round up.

Ready-mix. 13.75 yards delivered costs about $2,183, while 612 bags would cost about $4,053 and take roughly 24 hours of mixing. Bags only win below about 1.3 cubic yards.

A #4 grid at 18 inches each way needs about 1,187 linear feet of bar including laps: 60 twenty-foot sticks and about 98 chairs. Welded wire mesh instead takes 25 sheets of 5 x 10 ft.

The installed range on this page is for a 5-inch driveway with forms, #4 rebar and a broom finish. Tear-out of an old driveway, excavation and the street apron are extra.

Related Guides

Slab Estimating & Editorial Engineering Team

Construction Cost Estimators & Civil Engineering Analysts
Our team specializes in structural flatwork estimating, concrete mix designs, and civil building codes (ACI 302.1R, ASTM C94). All calculators and cost guides are rigorously validated against live contractor material price sheets, regional aggregate indexes, and real-world project bids.