Installed cost
$6,960 – $12,190
$7.50 – $14.00 / sq ft
Concrete (+10%)
18.33 yd³
Net 16.67 yd³ at 6 in
80-lb bags
825
1,100 × 60-lb
Best way to buy
Ready-mix
3 trucks, $2,895

A 30 × 30 ft slab (900 sq ft) is a popular detached shop: two cars or one car and a lift, plus benches and tools. Shops with a two-post lift or heavy equipment are usually poured 6 in thick with 4,000 PSI concrete, 18.33 yd³ here, so the lift anchors have enough concrete to grip.

Concrete for a 30x30 Slab at 4, 5 and 6 Inches

ThicknessNet volumeWith 10% wasteReady-mix order80-lb bags60-lb bags40-lb bagsInstalled
4 in 11.11 yd³ 12.22 yd³ 12.25 yd³ 550 734 1,100 $6,040–$11,040
5 in 13.89 yd³ 15.28 yd³ 15.5 yd³ 688 917 1,375 $6,500–$11,610
6 in (typical) 16.67 yd³ 18.33 yd³ 18.5 yd³ 825 1,100 1,650 $6,960–$12,190
Bag yields: 80 lb = 0.60 ft³, 60 lb = 0.45 ft³, 40 lb = 0.30 ft³, rounded up to whole bags. Ready-mix rounded up to the next quarter yard. Installed low end: plain broom-finish slab with ready-mix at $150/yd³ plus a $120 delivery fee, forms and labor at $3.50/sq ft. High end: the calculator's default scope (adds a vapor barrier and #4 rebar at 18 in, labor at $5.00/sq ft) plus 25% contractor overhead and profit. DIY materials: the cheaper of ready-mix or $6.50 80-lb bags, plus forms, up to vapor barrier and rebar. Site excavation and a gravel base are extra (about $1.40 to $3.30 per sq ft).

How Much Extra to Order

The table above adds 10%, the usual allowance for a formed slab on a graded base. Pick less only for rigid forms on a laser-flat base, more for soft or uneven ground:

Waste allowance (6 in slab)Concrete80-lb bags
0% (exact volume)16.67 yd³750
5%17.50 yd³788
10%18.33 yd³825
15%19.17 yd³863

Bags or a Ready-Mix Truck?

OptionWhat you buyConcrete bill
80-lb bags 825 bags at $6.50 + mixer rental $75 $5,438
Ready-mix 18.5 yd³ at $150 + $120 delivery $2,895

Ready-mix, without question. 825 bags would cost $5,438 and take about 33 hours of mixing, far longer than concrete stays workable, so the slab would end up with cold joints. Ready-mix trucks bring it as fast as the crew can place it (3 trucks of about 8–10 yd³ each). Try your own prices in the bags vs. ready-mix calculator.

What a 30x30 Slab Costs

Line item (6 in slab)BasisCost
Ready-mix concrete + delivery18.33 yd³ at $150 + $120$2,870
Forms120 lin ft at $2.20$264
Vapor barrier900 sq ft at $0.35$315
#4 rebar at 18 in900 sq ft at $1.25$1,125
Broom finish900 sq ft at $0.75$675
Labor (place & finish)900 sq ft at $5.00$4,500
Direct costBefore overhead and profit$9,749
  • Installed price: $6,960 – $12,190. The low end is a plain slab with lower-cost labor; the high end is the full scope above plus 25% contractor overhead and profit.
  • Site prep and gravel base (excavation and 4 in of compacted stone): about $1,260 – $2,970 more.
  • Thickened edge (12 in wide, 12–18 in deep) if the building sits on the slab: 2.4–4.7 yd³ more concrete, about $350 – $710, plus trenching and two #4 bars around the edge.
  • Permit, where one is needed: about $50 – $350.

Have a contractor's price? Put it into the concrete quote checker, or compare two or three bids side by side there.

Materials List for a 30 × 30 ft Slab

Concrete18.5 yd³ ready-mix, or 825 × 80-lb / 1,650 × 40-lb bags
Gravel base (4 in compacted)12.78 yd³, about 17.9 tons
Forms12 × 2x6 boards 12 ft long, 48 stakes, 96 screws (120 lin ft)
Rebar (#4 at 18 in)1,298 lin ft = 65 × 20-ft sticks, 121 chairs
Rebar (#4 at 12 in, heavy loads)1,947 lin ft = 98 × 20-ft sticks, 64 chairs
Or wire mesh (6x6)28 sheets of 5 × 10 ft, about $336 – $560
Vapor barrier900 sq ft plus 6 in laps
Control joints 4 panels of about 15 × 15 ft: 60 lin ft of saw cut, 1.5 in deep

Recommended Specs for a Shop Or Barn Floor

Thickness6 in for shops with heavy vehicles, lifts or machinery; 4-5 in for light storage
Strength4,000 PSI for heavy trucks and de-icing salt; 3,500 PSI air-entrained minimum
Base4 to 6 in of compacted crushed stone, plus a vapor barrier if the building will be heated
Reinforcement#4 rebar at 12-18 in on chairs; heavier where an engineer specifies it
EdgeThickened edge or footings at the walls; post-frame buildings set their posts on separate footings
  • Check the lift maker's anchor rules (minimum thickness, PSI and distance from joints) before placing the control joints.
  • Mark the lift location on the forms so no control joint runs under its posts.
  • Plan floor drains, an air line sleeve and the electrical feed before the pour.

Pour Day for a 30x30 Slab

  • Crew time: about 32 crew-hours to set forms, place, finish and cut joints (0.035 h per sq ft for a broom finish).
  • Trucks: 18.5 yd³ is 3 trucks, about 93–148 minutes of unloading in total. Concrete must be placed within 90 minutes of batching.
  • Reach: a truck chute reaches about 15–20 ft. At 30 ft wide, the middle is out of reach from one side, so plan access on two sides, a buggy, or a pump ($600 – $1,200).
  • Joints: saw-cut 4–12 hours after finishing with a wet saw, or 1–4 hours with an early-entry saw.
  • Curing: foot traffic after 24–48 hours, cars after 7 days, full strength at 28 days.

Price Your Own 30x30 Slab

The calculator below starts at 30 × 30 ft, 6 inches. Change the thickness, finish or reinforcement, pick your state for local prices, and the Live Estimate updates with a blueprint of the joint and rebar layout.

Concrete Slab Cost & Volume Estimator

Precision multi-layer project budgeting: Materials, Sub-Base, Reinforcement, Labor & Equipment

Picking a location sets the ready-mix, excavation and labor rates below to that area's typical level. You can still type your own local prices afterwards. Slab prices by state.

ft
ft
in
$
$ /sq ft
inches
$ /yd³
$ /lin ft
$ /sq ft

Closer spacing uses more steel and raises the rebar cost.

$
$ /sq ft
$

Not charged when bagged concrete is selected.

$
$
$
$ /sq ft
%
%
Live Estimate
Estimated Total Project Budget
$10,236.45
$11.37 / sq. ft.
$122.43 / m²
Based on U.S. national average rates
Order Volume (w/ Waste)
18.33 yd³
Net: 16.67 yd³
Or Bagged Equivalent
825 bags
80-lb pre-mix bags
Total Surface Area
900 sq ft (83.6 m²)
Order volume: 14.02 m³
Estimated Wet Weight
71,775 lbs
Perimeter: 120 ft
Concrete
Labor
Prep/Base
Rebar
Forms

A scaled plan of your slab: rebar grid at the spacing you chose, support chairs about every 3 to 4 ft, and the recommended control-joint saw cuts (2.5 times the thickness in inches, in feet, capped at 15 ft). It redraws as you change the inputs.

30x30 Slab Questions

About $6,960 to $12,190 installed for a 6-inch slab with forms, a broom finish and labor ($7.50 to $14.00 per sq ft), at U.S. average prices. DIY materials run about $3,130 to $4,570. Site prep and a gravel base add about $1,260 to $2,970.

At 4 inches thick with 10% waste: 550 bags of 80-lb mix, 734 bags of 60-lb mix or 1,100 bags of 40-lb mix. At 6 inches: 825 bags of 80-lb mix.

At 4 inches, 11.11 cubic yards (order 12.25 with waste); at 5 inches, 13.89 (order 15.50); at 6 inches, 16.67 (order 18.50). Ready-mix is sold in quarter yards, so round up.

Ready-mix. 18.5 yards delivered costs about $2,895, while 825 bags would cost about $5,438 and take roughly 33 hours of mixing. Bags only win below about 1.3 cubic yards.

A #4 grid at 18 inches each way needs about 1,298 linear feet of bar including laps: 65 twenty-foot sticks and about 121 chairs. Welded wire mesh instead takes 28 sheets of 5 x 10 ft.

6 inches with #4 rebar is the common choice for a shop with a car lift or heavy equipment. A light-use storage shop can be 4 to 5 inches. Follow your lift maker's anchor requirements.

Related Guides

Slab Estimating & Editorial Engineering Team

Construction Cost Estimators & Civil Engineering Analysts
Our team specializes in structural flatwork estimating, concrete mix designs, and civil building codes (ACI 302.1R, ASTM C94). All calculators and cost guides are rigorously validated against live contractor material price sheets, regional aggregate indexes, and real-world project bids.