Gravel Base Calculator
Find the cubic yards and tons of crushed stone to put under a slab, with extra for compaction so the base ends up at full depth.
A 4-inch compacted gravel base under a 20 × 20 ft slab takes about 5.68 cubic yards of crushed stone, or 7.95 tons, including 15% extra for compaction. At $35 to $55 per yard that is roughly $199 to $312.
Gravel Base Calculator
How the Base Is Calculated
The base spreads the slab's load and lets water drain away from its underside. Spread it in thin layers and run a plate compactor over each one. See how much gravel you need under a slab for stone types and when a base can be thinner.
How Much Gravel Under a Concrete Slab, by Size
| Slab | 4 in base | 6 in base |
|---|---|---|
| 10 × 10 ft | 1.4 yd³ (2.0 tons) | 2.1 yd³ (3.0 tons) |
| 12 × 16 ft | 2.7 yd³ (3.8 tons) | 4.1 yd³ (5.7 tons) |
| 20 × 20 ft | 5.7 yd³ (8.0 tons) | 8.5 yd³ (11.9 tons) |
| 24 × 24 ft | 8.2 yd³ (11.4 tons) | 12.3 yd³ (17.2 tons) |
| 30 × 40 ft | 17.0 yd³ (23.9 tons) | 25.6 yd³ (35.8 tons) |
| 40 × 60 ft | 34.1 yd³ (47.7 tons) | 51.1 yd³ (71.6 tons) |
Need a Full Project Cost Estimate?
This tool works out one part of the job. Our Concrete Slab Cost Calculator prices the whole slab: concrete, gravel base, forms, vapor barrier, reinforcement, finish, labor and delivery.