Waste Allowance & Its Cost

Order Volume
5.43 yd³
Net: 4.94 yd³
Extra Concrete
0.49 yd³
Costs about $74
If You Run Short
$200 – $320
Second delivery + short-load fee
Or in 80-lb Bags
245 bags

Where the Extra Concrete Goes

Ground is never perfectly flat: a base that dips a quarter inch over a large slab can swallow a surprising amount of concrete. Forms bow a little under the weight of wet concrete, some spills from the chute or wheelbarrow, and some stays in the pump or mixer. The allowance below covers those losses so you finish the pour in one go.

  • 5%: Rigid forms on a flat, well-compacted base
  • 10%: Typical formed slab (recommended)
  • 15%: Uneven or soft subgrade, curves, many edges
  • 20%: Dug trenches, footings, rough ground
Order volume
Net volume × (1 + waste % ÷ 100)
Then round up to the plant's order step.

More detail in our guide to the concrete waste factor.

Need a Full Project Cost Estimate?

This tool works out one part of the job. Our Concrete Slab Cost Calculator prices the whole slab: concrete, gravel base, forms, vapor barrier, reinforcement, finish, labor and delivery.

Open the Slab Cost Calculator →

Frequently Asked Questions

10% is the usual allowance for a formed slab. Use about 5% on a very flat, well-compacted base with rigid forms, and 15% or more on rough or dug ground.
Too much. A little leftover can go into a small pad or post footing, while running short costs a second delivery, possible short-load fees and a weak cold joint.
Yes. Add the same percentage before dividing by the bag yield, and round up to whole bags.