Cement, Sand, Stone & Water

Portland Cement
10 bags
94-lb bags
Sand
0.94 tons
0.70 yd³
Gravel / Stone
1.46 tons
1.05 yd³
Water
53 gallons
At a 0.50 water-cement ratio

How the Mix Is Calculated

Dry materials
Wet volume × 1.54 = dry volume, split by the ratio
Example 1:2:3: cement is 1/6 of the dry volume, sand 2/6 and stone 3/6. One 94-lb bag of portland cement is about 1 ft³.

Dry ingredients take up more room than the concrete they make, because sand fills the gaps between stones and cement paste fills the gaps in the sand. That is why the dry volume is about 54% more than the slab volume. Water is set by a water-to-cement ratio of about 0.50 by weight: less water makes stronger concrete, so add only enough to make it workable.

Which Mix Ratio to Use

  • 1:1.5:3: Rich mix for thin sections, steps and repairs
  • 1:2:3: Standard mix for slabs, driveways and posts
  • 1:2:4: General mix for footings and light slabs
  • 1:3:6: Lean fill under slabs, not for wearing surfaces

Site-mixed concrete varies from batch to batch. For slabs that carry cars or need a set strength, ready-mix (ordered by PSI, see the ready-mix calculator) or bagged mix (see the bags calculator) is more predictable.

Need a Full Project Cost Estimate?

This tool works out one part of the job. Our Concrete Slab Cost Calculator prices the whole slab: concrete, gravel base, forms, vapor barrier, reinforcement, finish, labor and delivery.

Open the Slab Cost Calculator →

Frequently Asked Questions

1:2:3 (one part cement, two parts sand, three parts stone by volume) is a common all-round mix for slabs, driveways and posts. 1:2:4 is leaner and used for footings and light slabs.
About 7 bags of 94-lb portland cement per cubic yard, including the dry-volume factor of 1.54 and no waste.
Loose dry ingredients have air gaps that disappear when the concrete is mixed and placed, so you need about 54% more dry material than the finished volume.
Aim for a water-to-cement ratio of about 0.50 by weight, about 5.6 gallons per 94-lb bag of cement. Too much water makes weaker concrete that cracks more.