Installed cost
$3,610 – $6,370
$7.50 – $13.50 / sq ft
Concrete (+10%)
8.15 yd³
Net 7.41 yd³ at 5 in
80-lb bags
367
489 × 60-lb
Best way to buy
Ready-mix
2 trucks, $1,358

A 12 × 40 ft slab (480 sq ft) is a single-car driveway from the street to a one-car garage, with room to open doors on both sides. Driveways are poured 5 in thick in most places; this one takes 8.15 yd³, and its long narrow shape gets a joint about every 12 ft.

Concrete for a 12x40 Slab at 4, 5 and 6 Inches

ThicknessNet volumeWith 10% wasteReady-mix order80-lb bags60-lb bags40-lb bagsInstalled
4 in 5.93 yd³ 6.52 yd³ 6.75 yd³ 294 392 587 $3,370–$6,070
5 in (typical) 7.41 yd³ 8.15 yd³ 8.25 yd³ 367 489 734 $3,610–$6,370
6 in 8.89 yd³ 9.78 yd³ 10 yd³ 440 587 880 $3,860–$6,680
Bag yields: 80 lb = 0.60 ft³, 60 lb = 0.45 ft³, 40 lb = 0.30 ft³, rounded up to whole bags. Ready-mix rounded up to the next quarter yard. Installed low end: plain broom-finish slab with ready-mix at $150/yd³ plus a $120 delivery fee, forms and labor at $3.50/sq ft. High end: the calculator's default scope (adds a vapor barrier and #4 rebar at 18 in, labor at $5.00/sq ft) plus 25% contractor overhead and profit. DIY materials: the cheaper of ready-mix or $6.50 80-lb bags, plus forms, up to vapor barrier and rebar. Site excavation and a gravel base are extra (about $1.40 to $3.30 per sq ft).

How Much Extra to Order

The table above adds 10%, the usual allowance for a formed slab on a graded base. Pick less only for rigid forms on a laser-flat base, more for soft or uneven ground:

Waste allowance (5 in slab)Concrete80-lb bags
0% (exact volume)7.41 yd³334
5%7.78 yd³350
10%8.15 yd³367
15%8.52 yd³384

Bags or a Ready-Mix Truck?

OptionWhat you buyConcrete bill
80-lb bags 367 bags at $6.50 + mixer rental $75 $2,461
Ready-mix 8.25 yd³ at $150 + $120 delivery $1,358

Ready-mix, without question. 367 bags would cost $2,461 and take about 15 hours of mixing, far longer than concrete stays workable, so the slab would end up with cold joints. Ready-mix trucks bring it as fast as the crew can place it (2 trucks of about 8–10 yd³ each). Try your own prices in the bags vs. ready-mix calculator.

What a 12x40 Slab Costs

Line item (5 in slab)BasisCost
Ready-mix concrete + delivery8.15 yd³ at $150 + $120$1,342
Forms104 lin ft at $2.20$229
Vapor barrier480 sq ft at $0.35$168
#4 rebar at 18 in480 sq ft at $1.25$600
Broom finish480 sq ft at $0.75$360
Labor (place & finish)480 sq ft at $5.00$2,400
Direct costBefore overhead and profit$5,099
  • Installed price: $3,610 – $6,370. The low end is a plain slab with lower-cost labor; the high end is the full scope above plus 25% contractor overhead and profit.
  • Site prep and gravel base (excavation and 4 in of compacted stone): about $670 – $1,580 more.
  • Permit, where one is needed: about $50 – $350.

Have a contractor's price? Put it into the concrete quote checker, or compare two or three bids side by side there.

Materials List for a 12 × 40 ft Slab

Concrete8.25 yd³ ready-mix, or 367 × 80-lb / 734 × 40-lb bags
Gravel base (4 in compacted)6.81 yd³, about 9.5 tons
Forms10 × 2x6 boards 12 ft long, 42 stakes, 84 screws (104 lin ft)
Rebar (#4 at 18 in)689 lin ft = 35 × 20-ft sticks, 70 chairs
Rebar (#4 at 12 in, heavy loads)1,027 lin ft = 52 × 20-ft sticks, 44 chairs
Or wire mesh (6x6)15 sheets of 5 × 10 ft, about $180 – $300
Vapor barrier480 sq ft plus 6 in laps
Control joints 4 panels of about 10 × 12 ft: 36 lin ft of saw cut, 1.25 in deep

Recommended Specs for a Driveway

Thickness4 in for cars; 5 in standard; 6 in for RVs and delivery trucks
Strength4,000 PSI air-entrained where de-icing salt is used, otherwise 3,500 PSI
Base4 to 6 in of compacted crushed stone
Reinforcement#4 rebar at 18 in (12 in for heavy loads or cold climates) on chairs
DrainageAt least 1/8 in per foot, away from the garage door
  • Keep the joints square to the length and at most 1.5 times the 12-ft width apart, so the panels do not crack across their middle.
  • Where the driveway meets the street apron or garage slab, use expansion joint material.
  • Use 4,000 PSI air-entrained concrete if you use de-icing salt.

Pour Day for a 12x40 Slab

  • Crew time: about 17 crew-hours to set forms, place, finish and cut joints (0.035 h per sq ft for a broom finish).
  • Trucks: 8.25 yd³ is 2 trucks, about 41–66 minutes of unloading in total. Concrete must be placed within 90 minutes of batching.
  • Reach: a truck chute reaches about 15–20 ft, enough for this slab if the truck can park beside it. If it can't, budget wheelbarrows or a line pump.
  • Joints: saw-cut 4–12 hours after finishing with a wet saw, or 1–4 hours with an early-entry saw.
  • Curing: foot traffic after 24–48 hours, cars after 7 days, full strength at 28 days.

Price Your Own 12x40 Slab

The calculator below starts at 12 × 40 ft, 5 inches. Change the thickness, finish or reinforcement, pick your state for local prices, and the Live Estimate updates with a blueprint of the joint and rebar layout.

Concrete Slab Cost & Volume Estimator

Precision multi-layer project budgeting: Materials, Sub-Base, Reinforcement, Labor & Equipment

Picking a location sets the ready-mix, excavation and labor rates below to that area's typical level. You can still type your own local prices afterwards. Slab prices by state.

ft
ft
in
$
$ /sq ft
inches
$ /yd³
$ /lin ft
$ /sq ft

Closer spacing uses more steel and raises the rebar cost.

$
$ /sq ft
$

Not charged when bagged concrete is selected.

$
$
$
$ /sq ft
%
%
Live Estimate
Estimated Total Project Budget
$5,353.97
$11.15 / sq. ft.
$120.06 / m²
Based on U.S. national average rates
Order Volume (w/ Waste)
8.15 yd³
Net: 7.41 yd³
Or Bagged Equivalent
367 bags
80-lb pre-mix bags
Total Surface Area
480 sq ft (44.6 m²)
Order volume: 6.23 m³
Estimated Wet Weight
31,900 lbs
Perimeter: 104 ft
Concrete
Labor
Prep/Base
Rebar
Forms

A scaled plan of your slab: rebar grid at the spacing you chose, support chairs about every 3 to 4 ft, and the recommended control-joint saw cuts (2.5 times the thickness in inches, in feet, capped at 15 ft). It redraws as you change the inputs.

12x40 Slab Questions

About $3,610 to $6,370 installed for a 5-inch slab with forms, a broom finish and labor ($7.50 to $13.50 per sq ft), at U.S. average prices. DIY materials run about $1,570 to $2,340. Site prep and a gravel base add about $670 to $1,580.

At 4 inches thick with 10% waste: 294 bags of 80-lb mix, 392 bags of 60-lb mix or 587 bags of 40-lb mix. At 5 inches: 367 bags of 80-lb mix.

At 4 inches, 5.93 cubic yards (order 6.75 with waste); at 5 inches, 7.41 (order 8.25); at 6 inches, 8.89 (order 10.00). Ready-mix is sold in quarter yards, so round up.

Ready-mix. 8.25 yards delivered costs about $1,358, while 367 bags would cost about $2,461 and take roughly 15 hours of mixing. Bags only win below about 1.3 cubic yards.

A #4 grid at 18 inches each way needs about 689 linear feet of bar including laps: 35 twenty-foot sticks and about 70 chairs. Welded wire mesh instead takes 15 sheets of 5 x 10 ft.

10 feet is the minimum and 12 feet is more comfortable, leaving room to open doors and step onto the slab. A 12 × 40 ft driveway covers a typical front setback.

Related Guides

Slab Estimating & Editorial Engineering Team

Construction Cost Estimators & Civil Engineering Analysts
Our team specializes in structural flatwork estimating, concrete mix designs, and civil building codes (ACI 302.1R, ASTM C94). All calculators and cost guides are rigorously validated against live contractor material price sheets, regional aggregate indexes, and real-world project bids.