Installed cost
$700 – $1,190
$8.50 – $15.00 / sq ft
Concrete (+10%)
1.09 yd³
Net 0.99 yd³ at 4 in
80-lb bags
49
66 × 60-lb
Best way to buy
Bags
$394 with mixer

An 8 × 10 ft slab (80 sq ft) is the floor for the smallest prefab storage sheds, a trash and recycling enclosure, or a grill station off the back patio. It is a one-day DIY job: 1.09 yd³ with waste, or 49 bags of 80-lb mix, which two people can mix and place with a rented drum mixer in an afternoon.

Concrete for an 8x10 Slab at 4, 5 and 6 Inches

ThicknessNet volumeWith 10% wasteReady-mix order80-lb bags60-lb bags40-lb bagsInstalled
4 in (typical) 0.99 yd³ 1.09 yd³ 1.25 yd³ 49 66 98 $700–$1,190
5 in 1.23 yd³ 1.36 yd³ 1.5 yd³ 62 82 123 $740–$1,240
6 in 1.48 yd³ 1.63 yd³ 1.75 yd³ 74 98 147 $780–$1,290
Bag yields: 80 lb = 0.60 ft³, 60 lb = 0.45 ft³, 40 lb = 0.30 ft³, rounded up to whole bags. Ready-mix rounded up to the next quarter yard. Installed low end: plain broom-finish slab with ready-mix at $150/yd³ plus a $120 delivery fee, forms and labor at $3.50/sq ft. High end: the calculator's default scope (adds a vapor barrier and #4 rebar at 18 in, labor at $5.00/sq ft) plus 25% contractor overhead and profit. DIY materials: the cheaper of ready-mix or $6.50 80-lb bags, plus forms, up to vapor barrier and rebar. Site excavation and a gravel base are extra (about $1.40 to $3.30 per sq ft).

How Much Extra to Order

The table above adds 10%, the usual allowance for a formed slab on a graded base. Pick less only for rigid forms on a laser-flat base, more for soft or uneven ground:

Waste allowance (4 in slab)Concrete80-lb bags
0% (exact volume)0.99 yd³45
5%1.04 yd³47
10%1.09 yd³49
15%1.14 yd³52

Bags or a Ready-Mix Truck?

OptionWhat you buyConcrete bill
80-lb bags 49 bags at $6.50 + mixer rental $75 $394
Ready-mix 1.25 yd³ at $150 + $120 delivery + $140 short-load fee $448

At 1.09 yd³, bags come out $54 cheaper, mostly because a small ready-mix order pays the delivery fee and a short-load fee. The trade-off is labor: 49 bags is about 2 hours of mixing for a small crew with one drum mixer, and every bag weighs 80 lb. Try your own prices in the bags vs. ready-mix calculator.

What an 8x10 Slab Costs

Line item (4 in slab)BasisCost
Ready-mix concrete + delivery1.09 yd³ at $150 + $120$283
Forms36 lin ft at $2.20$79
Vapor barrier80 sq ft at $0.35$28
#4 rebar at 18 in80 sq ft at $1.25$100
Broom finish80 sq ft at $0.75$60
Labor (place & finish)80 sq ft at $5.00$400
Direct costBefore overhead and profit$950
  • Installed price: $700 – $1,190. The low end is a plain slab with lower-cost labor; the high end is the full scope above plus 25% contractor overhead and profit.
  • Site prep and gravel base (excavation and 4 in of compacted stone): about $110 – $260 more.
  • Permit, where one is needed: about $50 – $350.

Have a contractor's price? Put it into the concrete quote checker, or compare two or three bids side by side there.

Materials List for an 8 × 10 ft Slab

Concrete1.25 yd³ ready-mix, or 49 × 80-lb / 98 × 40-lb bags
Gravel base (4 in compacted)1.14 yd³, about 1.6 tons
Forms4 × 2x4 boards 12 ft long, 14 stakes, 28 screws (36 lin ft)
Rebar (#4 at 18 in)120 lin ft = 7 × 20-ft sticks, 12 chairs
Or wire mesh (6x6)3 sheets of 5 × 10 ft, about $36 – $60
Vapor barrier80 sq ft plus 6 in laps
Control joints None needed: both sides are within the 10 ft joint spacing for 4 in

Recommended Specs for a Shed Floor

Thickness4 in; thicken the edge to 8-12 in under the walls in frost country, or follow your permit
Strength3,000 PSI; 3,500 PSI air-entrained where it freezes
Base4 to 6 in of compacted crushed stone
Reinforcement6x6 wire mesh, or #4 rebar at 18 in if a mower, ATV or car will park inside
Anchors1/2 in J-bolts in the wet concrete, 1-3/4 in in from the edge, about every 4-6 ft and within 12 in of each corner
  • Match the slab to the shed kit's floor frame, not its roof: the walls should sit on the slab with the siding lapping just past the edge so rain drips off instead of running underneath.
  • Set J-bolts or plan for wedge anchors if the shed must be tied down; many towns require it in high-wind areas.
  • At this size you can skip a ready-mix truck entirely; see the bags vs. truck numbers below.

Pour Day for an 8x10 Slab

  • Crew time: about 3 crew-hours to set forms, place, finish and cut joints (0.035 h per sq ft for a broom finish).
  • Reach: a truck chute reaches about 15–20 ft, enough for this slab if the truck can park beside it. If it can't, budget wheelbarrows or a line pump.
  • Joints: saw-cut 4–12 hours after finishing with a wet saw, or 1–4 hours with an early-entry saw.
  • Curing: foot traffic after 24–48 hours, cars after 7 days, full strength at 28 days.

Price Your Own 8x10 Slab

The calculator below starts at 8 × 10 ft, 4 inches. Change the thickness, finish or reinforcement, pick your state for local prices, and the Live Estimate updates with a blueprint of the joint and rebar layout.

Concrete Slab Cost & Volume Estimator

Precision multi-layer project budgeting: Materials, Sub-Base, Reinforcement, Labor & Equipment

Picking a location sets the ready-mix, excavation and labor rates below to that area's typical level. You can still type your own local prices afterwards. Slab prices by state.

ft
ft
in
$
$ /sq ft
inches
$ /yd³
$ /lin ft
$ /sq ft

Closer spacing uses more steel and raises the rebar cost.

$
$ /sq ft
$

Not charged when bagged concrete is selected.

$
$
$
$ /sq ft
%
%
Live Estimate
Estimated Total Project Budget
$997.67
$12.47 / sq. ft.
$134.24 / m²
Based on U.S. national average rates
Order Volume (w/ Waste)
1.09 yd³
Net: 0.99 yd³
Or Bagged Equivalent
49 bags
80-lb pre-mix bags
Total Surface Area
80 sq ft (7.4 m²)
Order volume: 0.83 m³
Estimated Wet Weight
4,253 lbs
Perimeter: 36 ft
Concrete
Labor
Prep/Base
Rebar
Forms

A scaled plan of your slab: rebar grid at the spacing you chose, support chairs about every 3 to 4 ft, and the recommended control-joint saw cuts (2.5 times the thickness in inches, in feet, capped at 15 ft). It redraws as you change the inputs.

8x10 Slab Questions

About $700 to $1,190 installed for a 4-inch slab with forms, a broom finish and labor ($8.50 to $15.00 per sq ft), at U.S. average prices. DIY materials run about $360 to $490. Site prep and a gravel base add about $110 to $260.

At 4 inches thick with 10% waste: 49 bags of 80-lb mix, 66 bags of 60-lb mix or 98 bags of 40-lb mix. At 6 inches: 74 bags of 80-lb mix.

At 4 inches, 0.99 cubic yards (order 1.25 with waste); at 5 inches, 1.23 (order 1.50); at 6 inches, 1.48 (order 1.75). Ready-mix is sold in quarter yards, so round up.

Bags are a little cheaper here: 49 bags cost about $394 with a rented mixer, against about $448 for a 1.25-yard ready-mix load with delivery and short-load fees. Mixing takes about 2 hours for a small crew.

A #4 grid at 18 inches each way needs about 120 linear feet of bar including laps: 7 twenty-foot sticks and about 12 chairs. Welded wire mesh instead takes 3 sheets of 5 x 10 ft.

Often not: many towns exempt sheds under 120 or 200 sq ft from a building permit, but zoning setbacks still apply and some places permit any concrete flatwork. Call your building department before you dig.

Related Guides

Slab Estimating & Editorial Engineering Team

Construction Cost Estimators & Civil Engineering Analysts
Our team specializes in structural flatwork estimating, concrete mix designs, and civil building codes (ACI 302.1R, ASTM C94). All calculators and cost guides are rigorously validated against live contractor material price sheets, regional aggregate indexes, and real-world project bids.