Installed cost
$12,160 – $21,400
$7.50 – $13.50 / sq ft
Concrete (+10%)
32.59 yd³
Net 29.63 yd³ at 6 in
80-lb bags
1,467
1,956 × 60-lb
Best way to buy
Ready-mix
5 trucks, $5,033

A 40 × 40 ft slab (1,600 sq ft) is a square shop, a farm equipment building or a commercial-style garage. Being square, it gets the same joint grid both ways; at 6 in it takes 32.59 yd³ and a crew of five or more with power trowels.

Concrete for a 40x40 Slab at 4, 5 and 6 Inches

ThicknessNet volumeWith 10% wasteReady-mix order80-lb bags60-lb bags40-lb bagsInstalled
4 in 19.75 yd³ 21.73 yd³ 21.75 yd³ 978 1,304 1,956 $10,530–$19,360
5 in 24.69 yd³ 27.16 yd³ 27.25 yd³ 1,223 1,630 2,445 $11,350–$20,380
6 in (typical) 29.63 yd³ 32.59 yd³ 32.75 yd³ 1,467 1,956 2,934 $12,160–$21,400
Bag yields: 80 lb = 0.60 ft³, 60 lb = 0.45 ft³, 40 lb = 0.30 ft³, rounded up to whole bags. Ready-mix rounded up to the next quarter yard. Installed low end: plain broom-finish slab with ready-mix at $150/yd³ plus a $120 delivery fee, forms and labor at $3.50/sq ft. High end: the calculator's default scope (adds a vapor barrier and #4 rebar at 18 in, labor at $5.00/sq ft) plus 25% contractor overhead and profit. DIY materials: the cheaper of ready-mix or $6.50 80-lb bags, plus forms, up to vapor barrier and rebar. Site excavation and a gravel base are extra (about $1.40 to $3.30 per sq ft).

How Much Extra to Order

The table above adds 10%, the usual allowance for a formed slab on a graded base. Pick less only for rigid forms on a laser-flat base, more for soft or uneven ground:

Waste allowance (6 in slab)Concrete80-lb bags
0% (exact volume)29.63 yd³1,334
5%31.11 yd³1,400
10%32.59 yd³1,467
15%34.07 yd³1,534

Bags or a Ready-Mix Truck?

OptionWhat you buyConcrete bill
80-lb bags 1,467 bags at $6.50 + mixer rental $75 $9,611
Ready-mix 32.75 yd³ at $150 + $120 delivery $5,033

Ready-mix, without question. 1,467 bags would cost $9,611 and take about 59 hours of mixing, far longer than concrete stays workable, so the slab would end up with cold joints. Ready-mix trucks bring it as fast as the crew can place it (5 trucks of about 8–10 yd³ each). Try your own prices in the bags vs. ready-mix calculator.

What a 40x40 Slab Costs

Line item (6 in slab)BasisCost
Ready-mix concrete + delivery32.59 yd³ at $150 + $120$5,009
Forms160 lin ft at $2.20$352
Vapor barrier1,600 sq ft at $0.35$560
#4 rebar at 18 in1,600 sq ft at $1.25$2,000
Broom finish1,600 sq ft at $0.75$1,200
Labor (place & finish)1,600 sq ft at $5.00$8,000
Direct costBefore overhead and profit$17,121
  • Installed price: $12,160 – $21,400. The low end is a plain slab with lower-cost labor; the high end is the full scope above plus 25% contractor overhead and profit.
  • Site prep and gravel base (excavation and 4 in of compacted stone): about $2,240 – $5,280 more.
  • Thickened edge (12 in wide, 12–18 in deep) if the building sits on the slab: 3.2–6.4 yd³ more concrete, about $480 – $950, plus trenching and two #4 bars around the edge.
  • Permit, where one is needed: about $50 – $350.

Have a contractor's price? Put it into the concrete quote checker, or compare two or three bids side by side there.

Materials List for a 40 × 40 ft Slab

Concrete32.75 yd³ ready-mix, or 1,467 × 80-lb / 2,934 × 40-lb bags
Gravel base (4 in compacted)22.72 yd³, about 31.8 tons
Forms16 × 2x6 boards 12 ft long, 68 stakes, 136 screws (160 lin ft)
Rebar (#4 at 18 in)2,346 lin ft = 118 × 20-ft sticks, 196 chairs
Rebar (#4 at 12 in, heavy loads)3,476 lin ft = 174 × 20-ft sticks, 121 chairs
Or wire mesh (6x6)45 sheets of 5 × 10 ft, about $540 – $900
Vapor barrier1,600 sq ft plus 6 in laps
Control joints 9 panels of about 13.3 × 13.3 ft: 160 lin ft of saw cut, 1.5 in deep

Recommended Specs for a Shop Or Barn Floor

Thickness6 in for shops with heavy vehicles, lifts or machinery; 4-5 in for light storage
Strength4,000 PSI for heavy trucks and de-icing salt; 3,500 PSI air-entrained minimum
Base4 to 6 in of compacted crushed stone, plus a vapor barrier if the building will be heated
Reinforcement#4 rebar at 12-18 in on chairs; heavier where an engineer specifies it
EdgeThickened edge or footings at the walls; post-frame buildings set their posts on separate footings
  • The middle of a 40-ft-wide slab is out of chute reach from any side; plan a pump or a buggy.
  • Power trowels (riding or walk-behind) are standard at this size; ask whether the bid includes them.
  • Curing compound or wet curing over 1,600 sq ft is worth asking about in the bid; a poorly cured shop floor dusts and curls.

Pour Day for a 40x40 Slab

  • Crew time: about 56 crew-hours to set forms, place, finish and cut joints (0.035 h per sq ft for a broom finish).
  • Trucks: 32.75 yd³ is 5 trucks, about 164–262 minutes of unloading in total. Concrete must be placed within 90 minutes of batching.
  • Reach: a truck chute reaches about 15–20 ft. At 40 ft wide, the middle is out of reach from one side, so plan access on two sides, a buggy, or a pump ($600 – $1,200).
  • Joints: saw-cut 4–12 hours after finishing with a wet saw, or 1–4 hours with an early-entry saw.
  • Curing: foot traffic after 24–48 hours, cars after 7 days, full strength at 28 days.

Price Your Own 40x40 Slab

The calculator below starts at 40 × 40 ft, 6 inches. Change the thickness, finish or reinforcement, pick your state for local prices, and the Live Estimate updates with a blueprint of the joint and rebar layout.

Concrete Slab Cost & Volume Estimator

Precision multi-layer project budgeting: Materials, Sub-Base, Reinforcement, Labor & Equipment

Picking a location sets the ready-mix, excavation and labor rates below to that area's typical level. You can still type your own local prices afterwards. Slab prices by state.

ft
ft
in
$
$ /sq ft
inches
$ /yd³
$ /lin ft
$ /sq ft

Closer spacing uses more steel and raises the rebar cost.

$
$ /sq ft
$

Not charged when bagged concrete is selected.

$
$
$
$ /sq ft
%
%
Live Estimate
Estimated Total Project Budget
$17,976.93
$11.24 / sq. ft.
$120.94 / m²
Based on U.S. national average rates
Order Volume (w/ Waste)
32.59 yd³
Net: 29.63 yd³
Or Bagged Equivalent
1467 bags
80-lb pre-mix bags
Total Surface Area
1,600 sq ft (148.6 m²)
Order volume: 24.92 m³
Estimated Wet Weight
127,600 lbs
Perimeter: 160 ft
Concrete
Labor
Prep/Base
Rebar
Forms

A scaled plan of your slab: rebar grid at the spacing you chose, support chairs about every 3 to 4 ft, and the recommended control-joint saw cuts (2.5 times the thickness in inches, in feet, capped at 15 ft). It redraws as you change the inputs.

40x40 Slab Questions

About $12,160 to $21,400 installed for a 6-inch slab with forms, a broom finish and labor ($7.50 to $13.50 per sq ft), at U.S. average prices. DIY materials run about $5,360 to $7,920. Site prep and a gravel base add about $2,240 to $5,280.

At 4 inches thick with 10% waste: 978 bags of 80-lb mix, 1,304 bags of 60-lb mix or 1,956 bags of 40-lb mix. At 6 inches: 1,467 bags of 80-lb mix.

At 4 inches, 19.75 cubic yards (order 21.75 with waste); at 5 inches, 24.69 (order 27.25); at 6 inches, 29.63 (order 32.75). Ready-mix is sold in quarter yards, so round up.

Ready-mix. 32.75 yards delivered costs about $5,033, while 1,467 bags would cost about $9,611 and take roughly 59 hours of mixing. Bags only win below about 1.3 cubic yards.

A #4 grid at 18 inches each way needs about 2,346 linear feet of bar including laps: 118 twenty-foot sticks and about 196 chairs. Welded wire mesh instead takes 45 sheets of 5 x 10 ft.

At 4 inches, 19.75 cubic yards net. At 6 inches, 29.63 net and 32.59 with waste, which is 5 truckloads.

Related Guides

Slab Estimating & Editorial Engineering Team

Construction Cost Estimators & Civil Engineering Analysts
Our team specializes in structural flatwork estimating, concrete mix designs, and civil building codes (ACI 302.1R, ASTM C94). All calculators and cost guides are rigorously validated against live contractor material price sheets, regional aggregate indexes, and real-world project bids.