Installed cost
$1,370 – $2,410
$7.50 – $13.50 / sq ft
Concrete (+10%)
2.44 yd³
Net 2.22 yd³ at 4 in
80-lb bags
110
147 × 60-lb
Best way to buy
Ready-mix
1 truck, $635

A 12 × 15 ft slab (180 sq ft) is a comfortable patio for a table for six and a grill, or the floor of a mid-size shed. At 4 in thick it takes 2.44 yd³ with waste, about 110 bags of 80-lb mix, which sits right around the point where a small ready-mix load starts to beat bags on price.

Concrete for a 12x15 Slab at 4, 5 and 6 Inches

ThicknessNet volumeWith 10% wasteReady-mix order80-lb bags60-lb bags40-lb bagsInstalled
4 in (typical) 2.22 yd³ 2.44 yd³ 2.5 yd³ 110 147 220 $1,370–$2,410
5 in 2.78 yd³ 3.06 yd³ 3.25 yd³ 138 184 275 $1,460–$2,530
6 in 3.33 yd³ 3.67 yd³ 3.75 yd³ 165 220 330 $1,550–$2,640
Bag yields: 80 lb = 0.60 ft³, 60 lb = 0.45 ft³, 40 lb = 0.30 ft³, rounded up to whole bags. Ready-mix rounded up to the next quarter yard. Installed low end: plain broom-finish slab with ready-mix at $150/yd³ plus a $120 delivery fee, forms and labor at $3.50/sq ft. High end: the calculator's default scope (adds a vapor barrier and #4 rebar at 18 in, labor at $5.00/sq ft) plus 25% contractor overhead and profit. DIY materials: the cheaper of ready-mix or $6.50 80-lb bags, plus forms, up to vapor barrier and rebar. Site excavation and a gravel base are extra (about $1.40 to $3.30 per sq ft).

How Much Extra to Order

The table above adds 10%, the usual allowance for a formed slab on a graded base. Pick less only for rigid forms on a laser-flat base, more for soft or uneven ground:

Waste allowance (4 in slab)Concrete80-lb bags
0% (exact volume)2.22 yd³100
5%2.33 yd³105
10%2.44 yd³110
15%2.56 yd³115

Bags or a Ready-Mix Truck?

OptionWhat you buyConcrete bill
80-lb bags 110 bags at $6.50 + mixer rental $75 $790
Ready-mix 2.5 yd³ at $150 + $120 delivery + $140 short-load fee $635

Ready-mix is $155 cheaper here and saves about 4.4 hours of mixing 110 bags. Bags only win below about 1.3 yd³, once the delivery and short-load fees are counted. Try your own prices in the bags vs. ready-mix calculator.

What a 12x15 Slab Costs

Line item (4 in slab)BasisCost
Ready-mix concrete + delivery2.44 yd³ at $150 + $120$487
Forms54 lin ft at $2.20$119
Vapor barrier180 sq ft at $0.35$63
#4 rebar at 18 in180 sq ft at $1.25$225
Broom finish180 sq ft at $0.75$135
Labor (place & finish)180 sq ft at $5.00$900
Direct costBefore overhead and profit$1,928
  • Installed price: $1,370 – $2,410. The low end is a plain slab with lower-cost labor; the high end is the full scope above plus 25% contractor overhead and profit.
  • Site prep and gravel base (excavation and 4 in of compacted stone): about $250 – $590 more.
  • Stamped finish instead of broom: about $2,590 – $3,930 installed.
  • Permit, where one is needed: about $50 – $350.

Have a contractor's price? Put it into the concrete quote checker, or compare two or three bids side by side there.

Materials List for a 12 × 15 ft Slab

Concrete2.5 yd³ ready-mix, or 110 × 80-lb / 220 × 40-lb bags
Gravel base (4 in compacted)2.56 yd³, about 3.6 tons
Forms6 × 2x4 boards 12 ft long, 20 stakes, 40 screws (54 lin ft)
Rebar (#4 at 18 in)254 lin ft = 13 × 20-ft sticks, 30 chairs
Or wire mesh (6x6)6 sheets of 5 × 10 ft, about $72 – $120
Vapor barrier180 sq ft plus 6 in laps
Control joints 4 panels of about 7.5 × 6 ft: 27 lin ft of saw cut, 1 in deep

Recommended Specs for a Patio

Thickness4 in
Strength3,000 PSI; 3,500 PSI air-entrained where it freezes
Base4 to 6 in of compacted crushed stone
Reinforcement6x6 wire mesh or fiber mix; #3-#4 rebar on expansive clay
Drainage1/8 to 1/4 in per foot away from the house
  • Slope a patio away from the house at about 1/4 in per foot, so the 12-ft depth drops about 3 in.
  • One control joint across the 15-ft side splits it into two panels of about 12 × 7.5 ft, close enough to square to keep random cracks away.
  • Under 200 sq ft many towns do not ask for a permit for a patio or shed slab, but check setbacks and HOA rules first.

Pour Day for a 12x15 Slab

  • Crew time: about 6 crew-hours to set forms, place, finish and cut joints (0.035 h per sq ft for a broom finish).
  • Trucks: 2.5 yd³ is 1 truck, about 13–20 minutes of unloading in total. Concrete must be placed within 90 minutes of batching.
  • Reach: a truck chute reaches about 15–20 ft, enough for this slab if the truck can park beside it. If it can't, budget wheelbarrows or a line pump.
  • Joints: saw-cut 4–12 hours after finishing with a wet saw, or 1–4 hours with an early-entry saw.
  • Curing: foot traffic after 24–48 hours, cars after 7 days, full strength at 28 days.

Price Your Own 12x15 Slab

The calculator below starts at 12 × 15 ft, 4 inches. Change the thickness, finish or reinforcement, pick your state for local prices, and the Live Estimate updates with a blueprint of the joint and rebar layout.

Concrete Slab Cost & Volume Estimator

Precision multi-layer project budgeting: Materials, Sub-Base, Reinforcement, Labor & Equipment

Picking a location sets the ready-mix, excavation and labor rates below to that area's typical level. You can still type your own local prices afterwards. Slab prices by state.

ft
ft
in
$
$ /sq ft
inches
$ /yd³
$ /lin ft
$ /sq ft

Closer spacing uses more steel and raises the rebar cost.

$
$ /sq ft
$

Not charged when bagged concrete is selected.

$
$
$
$ /sq ft
%
%
Live Estimate
Estimated Total Project Budget
$2,024.89
$11.25 / sq. ft.
$121.09 / m²
Based on U.S. national average rates
Order Volume (w/ Waste)
2.44 yd³
Net: 2.22 yd³
Or Bagged Equivalent
110 bags
80-lb pre-mix bags
Total Surface Area
180 sq ft (16.7 m²)
Order volume: 1.87 m³
Estimated Wet Weight
9,570 lbs
Perimeter: 54 ft
Concrete
Labor
Prep/Base
Rebar
Forms

A scaled plan of your slab: rebar grid at the spacing you chose, support chairs about every 3 to 4 ft, and the recommended control-joint saw cuts (2.5 times the thickness in inches, in feet, capped at 15 ft). It redraws as you change the inputs.

12x15 Slab Questions

About $1,370 to $2,410 installed for a 4-inch slab with forms, a broom finish and labor ($7.50 to $13.50 per sq ft), at U.S. average prices. DIY materials run about $610 to $890. Site prep and a gravel base add about $250 to $590.

At 4 inches thick with 10% waste: 110 bags of 80-lb mix, 147 bags of 60-lb mix or 220 bags of 40-lb mix. At 6 inches: 165 bags of 80-lb mix.

At 4 inches, 2.22 cubic yards (order 2.50 with waste); at 5 inches, 2.78 (order 3.25); at 6 inches, 3.33 (order 3.75). Ready-mix is sold in quarter yards, so round up.

Ready-mix. 2.5 yards delivered costs about $635, while 110 bags would cost about $790 and take roughly 4 hours of mixing. Bags only win below about 1.3 cubic yards.

A #4 grid at 18 inches each way needs about 254 linear feet of bar including laps: 13 twenty-foot sticks and about 30 chairs. Welded wire mesh instead takes 6 sheets of 5 x 10 ft.

Yes. A table for six needs about 10 x 12 ft with room to pull chairs out, so a 12 x 15 ft patio fits it with space left for a grill or two lounge chairs. For a separate seating group as well, look at 16 x 20 ft.

Related Guides

Slab Estimating & Editorial Engineering Team

Construction Cost Estimators & Civil Engineering Analysts
Our team specializes in structural flatwork estimating, concrete mix designs, and civil building codes (ACI 302.1R, ASTM C94). All calculators and cost guides are rigorously validated against live contractor material price sheets, regional aggregate indexes, and real-world project bids.