Concrete Slab Cost & Volume Estimator

Precision multi-layer project budgeting: Materials, Sub-Base, Reinforcement, Labor & Equipment

Picking a location sets the ready-mix, excavation and labor rates below to that area's typical level. You can still type your own local prices afterwards. Slab prices by state.

ft
ft
in
$
$ /sq ft
inches
$ /yd³
$ /lin ft
$ /sq ft

Closer spacing uses more steel and raises the rebar cost.

$
$ /sq ft
$

Not charged when bagged concrete is selected.

$
$
$
$ /sq ft
%
%
Live Estimate
Estimated Total Project Budget
$6,333.04
$10.99 / sq. ft.
$118.35 / m²
Based on U.S. national average rates
Order Volume (w/ Waste)
9.78 yd³
Net: 8.89 yd³
Or Bagged Equivalent
440 bags
80-lb pre-mix bags
Total Surface Area
576 sq ft (53.5 m²)
Order volume: 7.48 m³
Estimated Wet Weight
38,280 lbs
Perimeter: 96 ft
Concrete
Labor
Prep/Base
Rebar
Forms

A scaled plan of your slab: rebar grid at the spacing you chose, support chairs about every 3 to 4 ft, and the recommended control-joint saw cuts (2.5 times the thickness in inches, in feet, capped at 15 ft). It redraws as you change the inputs.

Garage Slab Sizes and Costs (5 in thick)

Project Size Concrete (+10% waste) DIY Materials Installed
1-car 12 × 24 ft (288 sq ft) 4.89 yd³ $1,010–$1,470 $2,240–$3,910
1.5-car / workshop 16 × 24 ft (384 sq ft) 6.52 yd³ $1,270–$1,890 $2,910–$5,120
2-car, compact 20 × 22 ft (440 sq ft) 7.47 yd³ $1,430–$2,130 $3,300–$5,820
2-car 24 × 24 ft (576 sq ft) 9.78 yd³ $1,800–$2,720 $4,250–$7,540
3-car 24 × 36 ft (864 sq ft) 14.67 yd³ $2,580–$3,970 $6,260–$11,170
Installed low end: plain broom-finish slab with ready-mix at $150/yd³ plus a $120 delivery fee, forms and labor at $3.50/sq ft. High end: the calculator's default scope (adds a vapor barrier and #4 rebar at 18 in, labor at $5.00/sq ft) plus 25% contractor overhead and profit. DIY materials: the cheaper of ready-mix or $6.50 80-lb bags, plus forms, up to vapor barrier and rebar. Site excavation and a gravel base are extra (about $1.40 to $3.30 per sq ft).

Recommended Specifications

Thickness5 in for cars; 6 in for a shop with lifts, heavy tools or trucks
Concrete strength3,500 PSI (the IRC minimum for garage floors in severe weather areas); 4,000 PSI if salty slush drips off cars
Vapor barrier6-mil or heavier polyethylene under the slab (IRC R506.2.3), especially if the garage will be heated or finished
EdgesThickened edge 12 in wide and 12 to 18 in deep for monolithic slabs, or a stem wall on footings in deep-frost areas
Reinforcement#4 rebar at 12 to 18 in centers, plus 2 bars around the edge
SlopeToward the door or a floor drain, so melt water runs out

Monolithic Slab or Stem Wall?

A monolithic slab pours the floor and a thickened edge in one go. It is the cheaper choice where frost is shallow. On a 24 × 24 ft garage, deepening the edge to 18 in takes about 4.06 extra cubic yards of concrete, plus trenching for the edge ($250 to $600 at 18 in deep in typical soil).

Where the frost line is deep (often 36 to 48 in or more in northern states), codes usually want footings below frost, so builders pour a footing and stem wall first and the floor slab inside it. That costs more but protects against frost heave. Your building department decides which one your garage needs. Estimate footing concrete with the footing calculator.

Before You Pour a Garage Floor

  • Floor drain or trench drain: it has to be set before the pour, with the slab sloped toward it.
  • Anchor bolts: sill-plate bolts or straps go into the wet edge concrete at the spacing your plans call for.
  • Door step-down: a small rebate at the overhead door keeps water from running under the door seal.
  • Coatings: if you plan an epoxy floor, ask for a steel-trowel finish and wait for the slab to dry fully first.

Frequently Asked Questions

A 24 x 24 ft garage floor at 5 inches thick costs about $4,250 to $7,540 installed, or $7 to $14 per sq ft. It needs 9.78 cubic yards of concrete before thickened edges.

Five inches is the usual recommendation for cars. Use 6 inches for a workshop with a car lift, heavy machines or trucks.

The IRC calls for a 6-mil vapor retarder under slabs of enclosed spaces, with some exceptions for unheated garages. Most builders install one anyway because it is cheap and stops moisture from damaging coatings and stored items.

A monolithic thickened-edge slab is cheaper and common where frost is shallow. In deep-frost areas codes usually require footings below the frost line, which means a stem wall foundation. Ask your building department.

Related Guides

Slab Estimating & Editorial Engineering Team

Construction Cost Estimators & Civil Engineering Analysts
Our team specializes in structural flatwork estimating, concrete mix designs, and civil building codes (ACI 302.1R, ASTM C94). All calculators and cost guides are rigorously validated against live contractor material price sheets, regional aggregate indexes, and real-world project bids.